Marshall Municipal Utilities internet crew burying fiber optic cable in rural Saline County

USDA Broadband Grant Status

MMU has received two grants from the USDA in 2019 and 2020 to try to help offset the cost of expanding Broadband to rural areas of Saline County.

Below are maps of the areas we have been approved to work in and our progress in completing them. There is a lot of empty conduit in areas of Grant 2, we will prioritize areas where customers have signed up, so please get on list.

Updated 2/23/26

Coleman Plumbing is working around Nelson. Kramer Services Group have finished their contracts. TNT Underground Construction is finishing around Slater. MMU crews are working around Napton, then will work on Junction area and the back to Elmwood area.

Fiber Grant progress Map

Newest Bid Info:

Bid 09-26-BBIT Contracts 2602-2603

2019 Grant Progress

Grant 1 Map

Backbone construction is complete for Grant 1. Come in and sign up anytime.

All Areascompletestop by to sign up

2020 Grant Progress

Grant 2 Map

2022 Contracts

2023 Contracts

2024 Contracts

2025 Contracts

NOTE: The maps in the table below show planned areas in Grant 2. However, the contracts for conduit do not necessarily match the entire area for any given year. For example, the Kittyhawk map shows the entire Kittyhawk to Quarry area, but only the blue lines on the map are planned for 2023. The completion percentages in the table only reflect the part of the areas that are planned this year. There may be some additional conduit installed by MMU personnel which could increase what gets done this year. Bold lines on maps are the areas of construction.

SouthLocationCompletionMap
 Mt Olive to Kittyhawk CompleteMap
 
Mt Olive to Blind Pony
CompleteMap
 Mt Olive
to Herndon
CompleteMap
 Water Tower to Smith ChapelCompleteMap
 Kittyhawk to QuarryCompleteMap
 
Kittyhawk to Smith Chapel
CompleteMap
 Drift to HerndonCompleteMap
 Quarry spursCompleteMap
 Drift to GrapeConduit completeMap
 Grape to HerndonConduit completeMap
 Herndon spursContractor did plowing; MMU will work on bores and remaining conduit this summerMap
 
Quarry to Junction
Conduit complete except Blackwater river crossing; fiber 50% completeMap
 Stuckeys to Smith Chapel2024 portion complete; conduit complete for remainderMap
 
Smith Chapel to Nelson West
2024 portion complete; conduit 80% complete for remainderMap
 North 
 
245th to Wildcat
Complete Map
 
Wildcat spur
Complete  Map
 
Wildcat to Klondike
Complete  Map

Wildcat to Gopher
CompleteMap
 
Gopher to Golden
Complete Map
 
Hwy NN to Hwy F
Conduit is complete except one rocky creek crossing  Map
 Hwy NN to MarinerConduit is complete except section around RR  Map
 
Mariner to Norton
conduit completewill be pulling fiber soonMap
West
 
EE to Elmwood
CompleteMap
 
EE to Blind Pony
CompleteMap
 
240th to Daybreak
CompleteMap
 
Golden to SE Malta Bend
CompleteMap
Elmwood to Blind Pony
 
Elmwood to Hwy VV
Some conduit is part of 2026 contracts currently in bid process; remainder will be bid in 2027Map
 
Daybreak to Elmwood
Conduit complete except RR crossing; fiber 90% complete; splicing 50% complete;Still waiting on RR permit, but we are working on backfeeding from the Elmwood side.Map
 
Elmwood to Blackburn
2024 conduit
contracted portion complete
Map
 EE/ElmwoodCompleteMap
 
Elmwood to Blackburn
Some conduit is part of 2026 contracts currently in bid process; remainder will be bid in 2027Map
 Blind Pony to 150th2024 portion: conduit complete; blowing fiber soon.Contractor did plowing on 145th Road, MMU will finish bores and pull fiber this summer;remainder is in 2026 contracts that are in the bid processMap

NW Malta Bend to SW Malta Bend
MMU will work on bores as time permitsMap
 
NW Malta Bend to Grand Pass
Conduit is part of 2026 contracts currently in bid processMap
 
NW Malta Bend to 290th
Conduit is part of 2026 contracts currently in bid processMap
 
Hwy VV to 150th
Conduit is part of 2026 contracts currently in bid processMap
 Hwy VV to AmberWill be bid in 2027Map
 Daybreak to SE Malta BendConduit complete except short section in Malta BendMap
 Daybreak to Blubell2024 portion: conduit complete;
remainder is part of 2026 contracts currently in bid processMap
 
Blubell to Grand Pass
2024 portion: conduit complete;remainder is part of 2026 contracts currently in bid processMap

Grand Pass spur
Conduit is part of 2026 contracts currently in bid processMap
East
Magnolia to NocturneCompleteMap
Magnolia to Hwy DCompleteMap
Magnolia to NeonCompleteMap
Nocturne to Nelson2024 portion complete;remainder: conduit 95%;fiber 20%Map
Nocturne to TT2024 portion except some splicing that connects to 2025 contract;remainder is part of 2025 Coleman contractsMap
Hwy TT to Nelson EastConduit is part of 2025 Coleman contracts5% completeMap
Neon to OrearvilleConduit is part of 2025 Coleman contractsMap
Neon to Fish CreekConduit is part of 2025 Coleman contractsMap
Orearville to ThompsonConduit completeMap
Orearville to OverlandConduit 90% complete;TNT working on cleaning up conduit and setting peds and vaultsMap
Orearville to MarinerConduit is complete except one rocky creek crossingMap
Contract 2504 – TNT – conduit 99% complete
Remaining Round 280 miles in west part of county will be bid in 2026