Miami #1 Substation Switchgear

Miami #1 Substation Switchgear

Miamisub1

Following a recommendation from Toth, MMU awarded the bid to Evans, Lipka, and Associates, Inc. for the new Eaton switchgear lineup in April 2024. In February 2025, MMU was notified that project drawings were non-conforming to the bid specifications. This required termination of the original bid award and a new request for bids. Following receipt of the new bids, and a new recommendation from Toth, MMU awarded the bid to Siemens. Delivery of the new switchgear is expected in March 2027 with project completion scheduled April 2027. Completion of this project will allow MMU to continue to provide the safe and reliable delivery of electricity to our customers.