"Providing Hometown Reliability"
Updated 4/22/24
Coleman Plumbing is working North of town along Hwy 41. He should be headed back to finish the side roads off YY after that. The new contractor, Kramer, has started East of town and working on the 2nd contract (2304). MMU crews are continuing to blow fiber and splice as weather allows. We have started blowing in fiber on Wildcat Road.
Backbone construction is complete for Grant 1. Come in and sign up anytime.
All Areas | complete | stop by to sign up |
NOTE: The maps in the table below show planned areas in Grant 2. However, the contracts for conduit do not necessarily match the entire area for any given year. For example, the Kittyhawk map shows the entire Kittyhawk to Quarry area, but only blue the lines on the map are planned for 2023. The completion percentages in the table only reflect the part of the areas that are planned this year. There may be some additional conduit installed by MMU personnel which could increase what gets done this year. Bold lines on maps are the areas of construction.
Contract 2201 (South) | Complete except portions of 2 side roads | ||||
Kittyhawk | 2023 portion complete | Map | |||
165th Rd | 2023 portion complete | Map | |||
Mt Olive | Complete | Map | |||
YY South | conduit 95% complete | fiber 95% complete | splicing 95% complete | Map | |
185th | conduit complete | fiber complete | splicing soon | Map | |
EE South | conduit 95% complete | fiber 95% complete | splicing 99% complete | Map | |
200th | 2023 portion complete | Map | |||
Contract 2202 (West) | Conduit 99% complete - one side road left | ||||
Daybreak | 2023 portion complete | Map | |||
230th | Complete | Map | |||
250th | 2023 portion complete | Map | |||
Golden North | conduit 95% complete | fiber 95% complete | splicing 95% complete | Map | |
Contract 2203 (North) | Conduit 85% complete | ||||
Wildcat | conduit complete | fiber 75% complete | Map | ||
Kite | conduit complete | Map | |||
41 North | conduit 65% complete | Map | |||
Klondike | conduit 95% complete | Map | |||
325th | conduit 99% complete | Map | |||
Contract 2301 (East) | Conduit complete | Map | |||
Hwy 240 | Map | ||||
230th Rd | Map | ||||
Contract 2302 (Southwest) | |||||
Contract 2303 (West) | |||||
Contract 2304 (Southeast) | Conduit 15% complete | Map | |||
Remaining Round 2 | Bids are out for about 24 miles of rocky areas around the quarry. The next round of normal ground will be bid late 2024. |