Marshall Municipal Utilities

"Providing Hometown Reliability"

Main Menu

  • Home
  • About MMU
  • Customer Service
  • Electricity
  • »Electric Production
  • »»Generating Capacity
  • »»»Units 1 & 2
  • »»»Unit 3
  • »»»Unit 4
  • »»»Unit 5
  • »»»Unit 6
  • »»»Units 7, 8, & 9
  • »»»Units 10 & 11
  • »»Pellet Facility
  • »Electric Distribution
  • »»Substations
  • »»Outages
  • »»Tree Trimming
  • »»Problem Report Form
  • Water
  • Wastewater
  • Natural Gas
  • Internet
  • Rates
  • Conservation and Safety
  • Sale Items
  • Site Map

Unit 4

Unit 4

Unit 4

Unit 4 is a 6 MW steam turbine that was installed in 1957. This unit burns stoker coal or natural gas. Recently, it has also been permitted to burn a paper pellets/coal blend, made from recycled paper at our pellet facility. Proper startup on this unit requires 18 hours. We traditionally used this unit in the summer when the city's electric use was high over several days. We are now using it for 3-4 months per year to burn paper pellets. The turbine and generator had a major overhaul in 1996, which put it in excellent condition.

Units 3 and 4 Cooling Tower

Units 3 & 4 Cooling Tower

Marshall Municipal Utilities
75 East Morgan
Marshall, MO 65340
Phone: (660)886-6966
Fax: (660)886-6724
E-mail: mmu@mmumo.net
Kyle Gibbs, General Manager

eXTReMe Tracker