NMS - Net Metering
APPLICATION:
Net metering is available in the distribution service territory of MMU at any point
on the Utility's existing facilities that have adequate capacity and suitable
voltage for delivery of service. A completed and approved application/agreement for
net metering is required. The form is available at MMU's business office.
AVAILABILITY OF SERVICE:
Net metering service is available to any customer that owns and operates a solar, wind,
or biomass generating facility or hydrogen fuel cell with a capacity of not more than
one hundred (100) kilowatts that is located on the customer's premises, is
interconnected and operates in parallel, with MMU's existing transmission and
distribution facilities, and is intended primarily to offset part or all of the
customer's own electrical power requirements. This rider is offered in compliance
with Consumer Clean Energy Act (386.887, RSMo Supp. 2002) and Missouri Public Service
Commission Rule 4 CSR 240-20.065.
DEFINITIONS
Net metering means measuring the difference between the electricity supplied by MMU
and the electricity generated by an eligible customer-generated and fed back to the
electric grid over the applicable billing period.
MONTHLY BILLING:
- The electric service charge shall be computed in accordance with the monthly
billing under the customer's effective standard rate schedule. Under this net
metering rider, only the kilowatthour (kWh) units of a customer-generator's bill are
affected.
- If the electricity supplied by MMU exceeds the electricity generated by the
customer-generator during the applicable billing period, the customer-generator shall
be billed for the net billable kWhs supplied by MMU in accordance with the rates and
charges under MMU's standard rate schedule applicable to then customer.
- If the electricity generated by the customer-generator exceeds the electricity
supplied MMU, the customer-gererator shall be credited for the net value of the
electric energy delivered to MMU during the applicable billing period at MMU's avoided
cost, with this credit appearing on the customer-generator's bill no later than the
following billing period.
SPECIAL CONDITIONS:
- The customer-generator must have a signed Standard Interconnection
Application/Agreement with MMU.
- The customer-generator is responsible for all costs associated with its generating
facility and is also responsible for all costs related to any modifications to the
facility that may be required by MMU for purposes of safety and reliability.
- A net metering facility shall meet all applicable safety and performance standards
established by the National Electric Safety Code, the National Electric Code, the
Institute of Electrical and Electronic Engineers, and Underwriters Laboratory.
- The customer-generator is responsible for obtaining liability insurance and such
other requirements that may be listed in the application/agreement for net metering.
TERMS OF SERVICE
Electric Service under this schedule is subject to all rules and regulations approved
by the Board of Public Works of Marshall, Missouri.